top of page

Suffolk Schoolhouse Retrofit

2024

IMG_5066 copy.HEIC

Suffolk schoolhouse

​

This 1838 house had experienced a comprehensive refurbishment in the 1960’s, losing many of its historical features and character.  

​

The owners wished to -

- decarbonise the heating system, 
- reduce heat loss from the building, 
- benefit from a heat pump for heating and hot water, 
- install photovoltaics on the roof and a battery to benefit from the energy harvested.  

​

They also wanted to regain the house’s historic character.  

Photos provided by client

Works

​

The roof tiles were removed and new clay tiles and pantiles installed over roof insulation.  Limitations on works possible to the side walls led to front and rear facade external insulation and internal insulation to the side walls.  Where internal insulation was installed, the build-up was moisture permeable to avoid condensation within the fabric.  Dormer windows were refurbished to give them improved thermal performance.

​

All windows and doors were replaced.  New windows were high performance triple glazed.

​

An air source heat pump was installed.  Underfloor heating was laid in the main central kitchen / dining room.  Other radiators were replaced with more efficient aluminium radiators to improve heating using the lower flow temperature of an air source heat pump.

​

Photovoltaic cells were installed flush with the new plain tiles and pantiles on the roof.  A battery was included to store energy produced to be used when needed.

​

MVHR decentralised fans were installed in each room to extract air and moisture, and maintain good air quality.  These were relatively simple to install, needing a 100mm core forming through the wall and a power supply to the fan.  Each fan has the ability to take heat out of the extracted air and pre-arm the incoming air.

Internally the opportunity to improve the layout was taken, knocking a new door opening from the hall into the back room, bringing light into the hall and views out to the garden.  The wc was tucked neatly under the stairs.

The removal of the corridor to the kitchen allowed it to be expanded and new tall window openings on the north side of the house brought light into this improved space.
 

Photos by Haysom Ward Miller

A temporary scaffold roof allowed good progress through the winter months, allowing works to roof and dormers to proceed.  Internally the secrets of the history of the building unfolded and revealed beautiful brick panels.

Internal wall insulation had to be moisture permeable, finished in lime plaster.  Underfloor heating was installed in the kitchen / dining space.

Photos by Haysom Ward Miller

© Haysom Ward Miller 2026

bottom of page